Geotechnical investigation for the installation of ERL
unit-2, Bangladesh phase-01

Major Work Done:
48 number of borehole with 48m to 60m depth.
Carry out the soil resistivity test
Carry out the thermal conductivity
5 nos of Cone Penetration Test (CPTu)
Laboratory Test: NMC, SPG, Grain Size Analysis, Atterberg Limit,
Consolidation, UCS Test, Direct Shear, Triaxial UU, Proctor Test, CBR etc.

Client : Technip FMC, France

Duration: April 2017 - Nov 2017

Project Location: Potenga, Chattogram

Geotechnical investigation for the installation of ERL unit-2