Geotechnical Investigation at Dhaka-Chittagong-Cox's Bazar Rail Line Project Preparatory Facility (DCCRPPF) Phase-1(C-1, C-2, C-4, C-5, C-7)

Major Work Done:
Cary out the geotechnical soil investigation of the proposed project.
297 nos of Borehole with 44m to 58m depth were done along with 165km length.
Determining the various parameters soil and safe bearing capacity of soil.
Laboratory Test: NMC, SPG, Grain Size Analysis, Atterberg Limit, Consolidation, UCS Test,
Direct Shear etc.
Water table with analysis report.

Client : Canarail, SMEC, Systra ACE Strategi JV Consultants

Duration: Dec 2018-Jul 2019

Project Location: Chittagong